• Manifest Group (opens in a new tab)
  • Projects
  • News
  • Careers
  • Contact
EL
  • Manifest Group
  • Projects
  • News
  • Careers
  • Contact
EL
  • Building
  • Energy
  • Infrastructure
  • Our team
  • Purpose and priorities
  • Our principles
  • Sustainability
  • Equality, diversity and inclusion
  • Health, safety and wellbeing
  • Social responsibility

We build complex projects with certainty. Across building, energy and infrastructure, we deliver lasting value.

What we do

  • Building
  • Energy
  • Infrastructure

Who we are

  • Our team
  • Purpose and Priorities
  • Careers

Projects

  • All Projects
  • Featured Projects

News

  • News
  • Articles

Contact

Neratziotissis 115151 24 Marousi, Greece (opens in a new tab)+30 211 345 6700info@manifest.gr

© 2026 Manifest Construction | Powered by Think Plus

Privacy | Terms | Cookies

Project

National Energy – SSSC-38 Solar Park

National Energy awarded Manifest Construction an EPC contract to design, supply, build and commission the 5.46 MWp SSSC-38 photovoltaic power station at Desmata, Stefani, in Corinthia. The aim was to deliver a modern single-axis tracker plant ready for production, operated and maintained over the long term by the same team.

National Energy – SSSC-38 Solar Park
LocationStefani, Corinthia
IndustryEnergy, renewables
Duration12 months
People on site30

What we did

  • Energy-yield studies, DC/LV/MV electrical design and geotechnical investigation.
  • Earthworks, internal roads, drainage, cable trenches and fencing of a 12.6-hectare site.
  • Pile driving and assembly of 151 tracker tables carrying 9,412 PV modules.
  • Installation of 17 Huawei inverters and a 5,600 kVA medium-voltage station.
  • Installation of SCADA, CCTV and communication networks.
  • Testing, energisation and handover of the as-built and O&M file.

Key takeaways

  • 5,458.96 kWp installed on single-axis East–West trackers.
  • Plant energised on 06/08/2025, with Taking Over on 31/12/2025.
  • One contractor from design through operation and maintenance.
  • Five specialist subcontractors coordinated on site.
  • Complete as-built health and safety file for the operating phase.